Section Detail Plans · Rev E

Burke Energy Campus —
Twelve-Zone Detail Plans

Zoomed layout schematics for every zone of the full-peninsula, 2 GW campus — equipment arrangement, process flow, footprint, and phase for each section, expanding on the Rev E master site plan.
The FixOurStreets216
Project
#WeThePeople · Neighborhoods First
FixOurStreets216 logo
Campus Net Output
2GW
Power Island
5–7× 7HA.03
Heat Recovery
HRSGCHP
Footprint
~770acres, full peninsula
Zones
12sections
Est. Fully-Loaded CapEx
~$26B
Full campus golden-hour aerial rendering
Rendered concept — full-peninsula master aerial, golden hour (prompt 00)
01Water Intake & Treatment 02PEM Electrolyzer Farm 03FastOx Gasification 047HA.03 Power Island 05Haber-Bosch Ammonia 06Grid Interconnection 07Offshore Wind Tie-In 08Marine Bunkering Pier 09H₂ / NH₃ Storage Field 10Hyperscale Data Center 11Public Lakefront Campus 12Research & Education Campus
Zone 1 · Phase 1 · 2029–2031
Lake Erie Water Intake & Treatment
West fill cellFoundational
Rendered concept — Water intake and treatment yard — shoreline pump station and treatment train
Rendered concept — Water intake and treatment yard — shoreline pump station and treatment train

Scaled up to serve a 2 GW campus: a submerged intake crib 300–600 m offshore draws below the thermocline, with fish-exclusion screens at <0.15 m/s protecting aquatic life. Raw water splits three ways downstream of the shoreline pump station — electrolyzer feed, data-center cooling makeup, and HRSG boiler feedwater — each polished to its own spec on a shared softening → RO → DI treatment train. Discharge reoxygenation returns all process water to full ecological health before it re-enters Lake Erie.

Submerged crib intakeRO + DI polishing3-way split: H₂ / DC cooling / HRSGGLWQA compliantReoxygenation discharge
Raw intake capacity110,000 gpm
Fish screen velocity< 0.15 m/s
Treated water quality< 1 µS/cm
Footprint40 acres
Est. CapEx$220M
LAKE ERIE Submerged intake crib 300–600 m offshore · fish screens SOFTENINGion exchange RO MEMBRANEreverse osmosis DI POLISH<1 µS/cm SPLIT HEADER → Zone 2 PEM Electrolyzer feed → Zone 4 HRSG boiler feedwater → Zone 10 DC cooling makeup ◀ Reoxygenation cascade — discharge returned to Lake Erie, GLWQA spec
Process flow, not to scale. Treatment train sized for combined PEM, HRSG, and data-center demand at full 2 GW build-out.
Zone 2 · Phase 1 · 2029–2031
PEM Electrolyzer Farm
West fill cell§45V eligible
Rendered concept — PEM electrolyzer stack halls — west fill cell
Rendered concept — PEM electrolyzer stack halls — west fill cell

Expanded to roughly 750 MW of proton-exchange-membrane electrolysis — about 11 t H₂/hr, 270 t/day — housed across three long, low pile-supported stack halls spread along the widened west fill cell now available under the full-peninsula footprint. Green hydrogen feeds the 7HA.03 power island's co-fire skid, the Haber-Bosch loop, industrial H₂ sales, and marine bunkering. O₂ byproduct is sold to Cleveland Clinic.

~750 MW PEM270 t H₂/day3 stack halls§45V eligibleO₂ to Cleveland Clinic
Electrolyzer input~750 MW
H₂ output270 t/day
Stack lifetime~80,000 hrs
Footprint130 acres
Est. CapEx$900M
STACK HALL A 8 × PEM stack skids STACK HALL B 8 × PEM stack skids STACK HALL C 6 × PEM stack skids H₂ header → co-fire skid (Zone 4) · Haber-Bosch (Zone 5) · storage (Zone 9) O₂ byproduct → Cleveland Clinic
Three stack halls (22 skids total) spread across the widened west fill cell. Not to scale.
Zone 3 · Phase 2 · 2030–2032
Sierra Energy FastOx Gasification
Mid-peninsulaZero landfill
Rendered concept — FastOx gasification shaft towers and tipping dock
Rendered concept — FastOx gasification shaft towers and tipping dock

FastOx shaft gasification converts Cleveland MSW at >2,200°C using oxygen and steam injection — no preprocessing required. Waste descends through drying, pyrolysis, gasification, and partial-oxidation zones, producing clean syngas (H₂ + CO) and inert vitrified slag for road aggregate. Syngas feeds the Haber-Bosch loop after water-gas shift and CO₂ removal. The larger peninsula footprint allows a second gasifier train to be pre-graded for future capacity.

FastOx shaft gasifier ×2 trainsMSW feedstock>2,200°CSyngas → Haber-BoschVitrified slag
MSW throughput~1,400 t/day
Operating temp> 2,200 °C
OutputSyngas + vitrified slag
Footprint40 acres
Est. CapEx$520M
MSW TIPPINGtruck receiving dockno preprocessing SHAFTGASIFIERTRAIN 1 >2,200°C SHAFTGASIFIERTRAIN 2 reserve / phase 2b SYNGAS CLEANUPwater-gas shiftCO₂ removal → Zone 5 Haber-Bosch synthesis loop Vitrified slag —road aggregate output Cleveland MSW gate fees → cost center becomes revenue stream Zero liquid discharge design
Two gasifier trains — one active, one pre-graded reserve for future MSW volume. Not to scale.
Zone 4 · Phase 1 · 2029–2033 · SMR-ready
GE Vernova 7HA.03 Power Island
ANCHORMid-peninsulaHRSG · CHP
Rendered concept — GE Vernova 7HA.03 power island — turbine row with HRSG stacks
Rendered concept — GE Vernova 7HA.03 power island — turbine row with HRSG stacks

The campus's primary generation: 5–7 GE Vernova 7HA.03 combined-cycle blocks (430 MW ISO simple-cycle each), staged across the widened mid-peninsula power yard to deliver approximately 2 GW net. Each gas turbine's ≈630°C exhaust is captured by a dedicated heat-recovery steam generator (HRSG); steam from a common header drives bottoming steam turbines for extra output and bleeds process steam for campus hot water and district heating. All units are hydrogen co-fire capable, and a reserved, pre-graded interior parcel keeps the small-modular-reactor upgrade path open. Mainspring + Hyliion KARNO fuel-flexible gensets plus BESS provide N+1 backup and full island capability.

5–7 × 7HA.03 · 430 MW ISO eachHRSG on every unitCommon steam header≈2 GW netH₂ co-fire capableSMR-reserve parcelMainspring + KARNO N+1
Configuration5–7 × 1×1 CCGT (GT+ST+HRSG)
Per-unit rating430 MW ISO simple-cycle
Campus net output≈2 GW
Exhaust to HRSG≈630 °C
Footprint150 acres
Est. CapEx$2.6B
POWER ISLAND — 6 UNITS SHOWN (5–7 RANGE) STEAM HDR GT17HA.03 HRSG GT27HA.03 HRSG GT37HA.03 HRSG GT47HA.03 HRSG GT57HA.03 HRSG GT6optional HRSG STEAM TURBINEbottoming cycle + district heat bleed SMR RESERVE PARCELpre-graded · zero-carbon path SWITCHYARD→ Zone 6 Mainspring + Hyliion KARNO backup fleet sized N+1 · full island capability BESSgrid-forming buffer H₂ co-fire header (from Zone 2) feeds all 5–7 fuel skids
Six 7HA.03 combined-cycle blocks shown (mid-point of the 5–7 range); each unit has its own HRSG feeding a shared steam header. Not to scale.
Zone 5 · Phase 2 · 2030–2032
Haber-Bosch Green Ammonia Synthesis
Mid-peninsulaCircular economy
Rendered concept — Haber-Bosch ammonia synthesis and cryogenic storage
Rendered concept — Haber-Bosch ammonia synthesis and cryogenic storage

An expanded ~2,200 t/day green ammonia plant combines electrolytic H₂ with nitrogen from an on-site Air Separation Unit. The synthesis loop runs 150–300 bar, 400–500°C over an iron catalyst; unreacted gas recycles. Ammonia serves fertilizer, marine-bunkering hydrogen-carrier, and pipeline-export markets simultaneously. The FastOx syngas-to-ammonia integration keeps Cleveland's MSW-to-fertilizer loop closed.

~2,200 t/day NH₃150–300 bar synthesisAir Separation UnitH₂ carrierFertilizer + marine export
NH₃ output~2,200 t/day
Synthesis conditions150–300 bar, 400–500°C
Per-pass conversion15–25%, recycled
Footprint38 acres
Est. CapEx$780M
AIR SEP UNITN₂ from atmosphere H₂ FEEDfrom Zone 2 + Zone 3 SYNTHESIS LOOP 150–300 bar 400–500°C, Fe catalyst 15–25% per pass ↺ unreacted gas recycle CRYO NH₃STORAGE SPHERE Fertilizer pipeline exportNE Ohio industrial corridor MC-331 tanker loadoutvapor recovery · e-shutdown → Zone 8 marine bunkering
Process schematic. IDLH 300 ppm NH₃ zone — truck/pier loadout bays are the most safety-critical areas on the campus.
Zone 6 · Phase 1 · 2029–2031
Grid Interconnection & Substation
SE gateway areaIslanding-capable
Rendered concept — Grid interconnection and 345kV substation yard
Rendered concept — Grid interconnection and 345kV substation yard

A new, larger point of common coupling (PCC) on the Shoreway corridor ties the 2 GW campus into Cleveland Public Power and FirstEnergy, sized well above the original 500 MW design. IEEE 1547-2018 islanding protection lets the campus disconnect and continue serving all internal loads autonomously during utility outages. The LEEDCo Icebreaker Wind submarine cable also lands and terminates here.

345kV substation, expanded baysIEEE 1547-2018 Cat IIICPP + FirstEnergyIsland modeIcebreaker Wind landing
Interconnect voltage345 kV
Firm export/importup to 2 GW
Footprint16 acres
Est. CapEx$220M
345 kV SUBSTATION YARD XFMR 1XFMR 2BREAKERBREAKER → Shoreway corridor / CPP + FE IEEE 1547-2018 Cat III islanding protection anti-islanding · fault current limiting · freq. response ◀ LEEDCo Icebreaker Wind submarine cable landing (Zone 7) ↑ Zone 4 power island tie-in · ↑ Zone 10 data-center feed
Substation yard schematic. Not to scale.
Zone 7 · Phase 2 · 2030–2032
Lake Erie Offshore Wind Tie-In
North bulkheadCurtailment absorption
Rendered concept — Offshore wind cable landing, Lake Erie
Rendered concept — Offshore wind cable landing, Lake Erie

Onshore landing for the LEEDCo Icebreaker Wind submarine cable — six turbines generating up to 126 MW roughly 13 km offshore. The now-larger electrolyzer farm (Zone 2) directly absorbs curtailed offshore generation that would otherwise be wasted, converting storage-less wind into storable hydrogen during high-wind, low-demand periods.

LEEDCo Icebreaker126 MW OSWSubmarine cable landingCurtailment → H₂
Offshore capacityup to 126 MW
Distance offshore~13 km
Footprint8 acres
Est. CapEx$55M
LAKE ERIE — ~13 KM TO ICEBREAKER WIND ARRAY 6 × turbines, 126 MW submarine cable CABLE LANDINGtermination station → Zone 6 substation CURTAILMENT ABSORPTION excess wind → Zone 2 electrolyzer rather than curtailed
Long-game scaling: excess offshore wind becomes storable green hydrogen instead of curtailed generation.
Zone 8 · Phase 4 · 2033–2034
Marine H₂ / NH₃ Bunkering Pier
North bulkheadIMO 2050
Rendered concept — Marine H2/NH3 bunkering pier
Rendered concept — Marine H2/NH3 bunkering pier

Built along the full peninsula's north bulkhead on Lake Erie, coordinated with the US Army Corps and Port of Cleveland. An expanded hydrogen and liquid-ammonia bunkering facility makes Cleveland the first Great Lakes port to offer green hydrogen marine fuel at scale, serving bulk carriers, container vessels, and passenger ferries as the IMO's 2050 decarbonization targets drive fleet conversion.

H₂ bunkeringLiquid NH₃ transferIMO 2050Great Lakes fleetArmy Corps bulkhead
Berths2 (bulk + ferry)
Fuel typesH₂ (compressed) · NH₃ (liquid)
Footprint20 acres
Est. CapEx$360M
LAKE ERIE — NORTH BULKHEAD ferry bulk carrier PIER DECK — 2 BERTHS H₂ FUELING STATIONIMO-compliant, compressedfrom Zone 9 storage field NH₃ CRACKING UNITon-demand, for H₂-combustion ships liquid NH₃ transfer arm Vapor recovery+ emergencyshutdown Feed lines from Zone 9 (H₂/NH₃ storage) · Zone 5 (Haber-Bosch) loadout
Pier elevation schematic, two berths shown. Not to scale.
Zone 9 · Phase 2 · 2030–2032
H₂ & NH₃ Storage Field
Mid-peninsulaGrid-scale buffer
Rendered concept — H2 and NH3 storage field
Rendered concept — H2 and NH3 storage field

Expanded high-pressure H₂ tube storage at 350 bar plus cryogenic liquid-ammonia tanks, sized for 72-hour buffer capacity at the full 2 GW production rate. Functions as a grid-scale virtual battery — surplus production fills storage during low-demand periods, and stored H₂ raises the 7HA.03 fleet's hydrogen co-fire fraction during peaks, qualifying for PJM ancillary-services payments.

350 bar H₂ tubesCryo liquid NH₃72-hr buffer @ 2 GW scalePJM ancillary services
H₂ storage pressure350 bar
Buffer duration72 hours
Footprint34 acres
Est. CapEx$480M
H₂ TUBE STORAGE — 350 BAR CRYOGENIC LIQUID NH₃ TANKS DISPATCH LOGIC low demand → fill storage peak demand → raise Zone 4 H₂ co-fire grid event → PJM ancillary dispatch → Zone 4 power island fuel skids → Zone 8 marine bunkering pier
Storage field layout, decoupling electrolyzer schedule from turbine demand. Not to scale.
Zone 10 · ANCHOR · Phase 1–3 · 2030–2035
Hyperscale Data Center — 2 GW
ANCHOREast pointSub-1.1 PUE
Rendered concept — Hyperscale data center halls — east point
Rendered concept — Hyperscale data center halls — east point

The anchor tenant and economic engine, now phased 500 → 1,200 → 2,000 MW IT load across the widened east point of the peninsula. Powered directly by the on-site 7HA.03 power island, it needs no scarce grid capacity. Lake Erie deep-water cooling holds sub-1.1 PUE: raw intake → traveling screens → RO filtration → heat-exchanger battery → CRAH + direct-liquid-cooling manifolds → warm return → reoxygenation cascade → UV → submerged diffuser. DLC for AI GPU clusters at up to 130 kW/rack.

2 GW IT loadSub-1.1 PUELake Erie cooling130 kW/rack DLC7HA.03 + SMR-reserve power
Phase 1 IT load500 MW
Phase 2 IT load1,200 MW
Phase 3 IT load2,000 MW
Footprint180 acres
Est. CapEx$19B (tenant-financed)
WHITE SPACE — PHASED HALLS HALL 1500 MW · Phase 1 HALL 2+700 MW · Phase 2 HALL 3+800 MW · Phase 3 SUBSTATION TIE-INfrom Zone 6 + Zone 4 COOLING PLANT Lake intake → screens → RO → heat-exchanger battery → CRAH + DLC manifolds → warm return → reoxygenation → UV → diffuser sub-1.1 PUE · 130 kW/rack DLC for AI GPU clusters Fiber duct bank→ Cleveland One carrier hotel Reoxygenated discharge→ Lake Erie, GLWQA spec
Three phased halls shown; layout is illustrative — final hall count set by hyperscale tenant design. Not to scale.
Zone 11 · Phase 3 · 2031–2034
Public Lakefront Campus
North edgeCivic
Rendered concept — Public lakefront promenade and Energy Discovery Centre
Rendered concept — Public lakefront promenade and Energy Discovery Centre

The public amenities zone faces Lake Erie along the now much longer northern edge of the full-peninsula campus. An Energy Discovery Centre lets visitors walk a glass-floored deck above the electrolyzer farm, watching hydrogen being produced from Lake Erie water — a natural Great Lakes Science Center partnership. Solar canopies cover parking and gathering areas; buildings draw on Zone 4's CHP district heat. The extended shoreline opens far more public lakefront than the original NE-corner-only design.

Energy Discovery CentreGlass-floor viewing deckGreat Lakes Science CenterZero-carbon buildingsExtended promenade
Lakefront opened~2.4 miles
Footprint70 acres
Est. CapEx$260M
LAKE ERIE — EXTENDED NORTH PROMENADE ENERGY DISCOVERYCENTRE glass-floor deck over Zone 2 electrolyzer farm sightline down ▼ HOTEL +CIVIC HALL CHP district heat from Zone 4 SOLAR CANOPY — PARKING Full-peninsula promenade opens ~2.4 miles of Lake Erie shoreline previously inaccessible to the public
Civic zone layout along the extended north shoreline. Not to scale.
Zone 12 · Phase 3 · 2031–2034
Research & Education Campus
South edgeLive testbed
Rendered concept — Research and education campus cluster
Rendered concept — Research and education campus cluster

Case Western Reserve University co-operates a Clean Energy Research Institute with Cleveland Clinic; CWRU's Great Lakes Energy Institute gets a full-scale operating PEM electrolyzer farm as a live testbed — something no university lab can replicate. Cleveland State's Midwest Hydrogen Center of Excellence also anchors here. The larger peninsula gives the research campus direct sightlines to both Zone 2 (electrolyzer) and Zone 4 (power island) for real-time data collection.

Case Western GLEICleveland ClinicCSU H₂ CenterLive PEM + turbine testbedDOE funding anchor
Anchor institutionsCWRU · Cleveland Clinic · CSU
Student pipelineCMSD → CWRU, 5,000+ students
Footprint40 acres
Est. CapEx$300M
CWRU GREAT LAKESENERGY INSTITUTE w/ Cleveland Clinic CSU MIDWEST H₂CENTER OF EXCELLENCE CLASSROOM +APPRENTICE LAB CMSD junior technician cohort ↓ live data feed Zone 2 PEM electrolyzer farm — membrane test-cell insertion points real fouling / pressure-cycling data Zone 4 power island — 7HA.03 H₂ co-fire performance monitoring instrumentation 5,000+ student CMSD → CWRU pipeline · DOE funding anchor advanced manufacturing turbine / PEM component R&D
Campus cluster with instrumented data links into the live electrolyzer and power-island operations. Not to scale.
Burke Lakefront Airport (KBKL) · Cleveland, Ohio · 41°31′N 81°41′W · Concept detail plans, not to scale
Rev E — full-peninsula footprint · 2 GW campus · 5–7 × GE Vernova 7HA.03 combined-cycle w/ HRSG
The FixOurStreets216 Project · #WeThePeople · Neighborhoods First